8 air flow fault tests, 1 blower proof switch test, 2 blocked inlet switch test – AERCO BMK 1000 User Manual

Page 84

Advertising
background image

Benchmark 750/1000 Boiler Installation, Operation & Maintenance Manual

CHAPTER 6 – SAFETY DEVICE TESTING

Page 84 of 192

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

OMM-0082_0J

05/21/2014

Ph.: 800-526-0288

GF-130

6.8 AIR FLOW FAULT TESTS

These tests check the operation of the Blower Proof Switch and Blocked Inlet Switch shown in
Figure 6-3.

6.8.1 Blower Proof Switch Test

Blower Proof Switch

Test

1. Disable the blower output drive voltage as follows:

a) Press the MENU key until CONFIGURATION MENU is displayed.

b)

Press the ▲ arrow key until the ANALOG OUTPUT function is displayed, then
press the CHANGE key.

c)

Press the ▼ arrow key until OFF is displayed, then press the ENTER key.

2. Start the unit in the Manual Mode at a valve position between 25% and 30%.

3. The unit should shut down and lockout, showing AIRFLOW FAULT DURING PURGE in

the display.

4. The unit should perform one IGNITION RETRY cycle and then shut down, since the

blower is disabled. The unit will then display AIRFLOW FAULT DURING PURGE.

5. Re-enable the blower output drive voltage by performing the following steps:

a) Press the MENU key until CONFIGURATION MENU is displayed.

b) Press the

▲ arrow key until the ANALOG OUTPUT function is displayed, then

press the CHANGE key.

c)

Press the ▲ arrow key until VALVE POSITION 0-10V is displayed, then press the
ENTER key.

d) Press the CLEAR button to clear the airflow fault.

6. Once the unit has proved flame, turn off the blower again by going to the Configuration

Menu, Analog Output menu item and select OFF.

7. The Blower Proof Switch will open and the blower should stop. The unit should shut down

and display AIRFLOW FAULT DURING RUN.

8. Go to the Configuration Menu, Analog Output item and select VALVE POSITION 0-10v.

6.8.2 Blocked Inlet Switch Test

This test will be run in simulated fire mode, with the Blocked Inlet Switch isolated from the rest
of the control circuitry.

Blocked Inlet Switch

Test

1. Turn off the main ON/OFF switch on the front of the Control Panel.

2. For units that get combustion air from a Combustion Air Duct, remove that duct, located

on the rear panel of the boiler (see Figure 6.4, below). For units that have an air filter in
place of a Combustion Air Duct (not shown), remove the air filter.

Advertising