Conventions and Terminology

Step 2

Install and connect the PDUs for the display and first row table assembly. See

Step 1

through

Step 3

in

Chapter 9, “Routing Power and Signal Cables”

to install the PDUs and

Step 4

in

Chapter 9, “Routing

Power and Signal Cables”

to connect the cables.

Step 3

Connect the projector to the projector bracket and connect the projector and bracket to the table
assembly. See

Step 2

and

Step 3

in

Chapter 8, “Assembling the Remaining Cisco TelePresence

Elements”

to connect the projector to the table assembly and

Step 4

in

Chapter 9, “Routing Power and

Signal Cables”

to connect the cables.

Step 4

Place the Cisco Unified IP Phone on the first row table and connect the phone cable. See

Step 4

in

Chapter 9, “Routing Power and Signal Cables”

to connect the cable.

Step 5

Install the privacy panels for the first row table. See

Step 15

through

Step 18

in

Chapter 6, “Building the

First Row Table Assembly.”

Step 6

Install the speaker boards and speakers. See

Step 8

through

Step 10

in

Chapter 8, “Assembling the

Remaining Cisco TelePresence Elements.”

Step 7

Install the projector screen. Refer to the projector screen installation guide that is packaged with the
assembly.

Step 8

Connect the power cables for the codecs, lighting and table leg power connections by completing

Step 4

in

Chapter 9, “Routing Power and Signal Cables.”

Step 9

Connect the signal cables for the first row table by completing

Step 5

in

Chapter 9, “Routing Power and

Signal Cables.”

Step 10

Assemble the camera targets by completing

Step 15

in

Chapter 8, “Assembling the Remaining

Cisco TelePresence Elements.”

Step 11

Perform first-time setup using the instructions in

Chapter 10, “First-Time Setup.”

Conventions and Terminology

The directions left and right in this guide are synonymous with participant’s left and participant’s
right
. They refer to the assembly as you face the Plasma displays.

Cable connections to the Codecs are labeled with a color-coded symbol system.

A single dot on a green background indicates a center element.

Two dots on a white background indicate a left element.

Three dots on a red background indicate a right element.

Figure 1-2

Cable Connection Labeling System

Tools and Equipment List

To assemble the Cisco TelePresence System 3200, you need the following tools and equipment:

Uncrating and Unpacking:

Claw hammer or small pry bar