Flowserve S-series PolyChem User Manual

Page 17

Advertising
background image

USER INSTRUCTIONS POLYCHEM S-SERIES ENGLISH 71569207 11-08

Page 17 of 52

flowserve.com

f) After leveling the baseplate, tighten the anchor

bolts. If shims were used, make sure that the
baseplate was shimmed near each anchor bolt
before tightening. Failure to do this may result in
a twist of the baseplate, which could make it
impossible to obtain final alignment.

g) Check the level of the baseplate to make sure

that tightening the anchor bolts did not disturb the
level of the baseplate. If the anchor bolts did
change the level, adjust the jackscrews or shims
as needed to level the baseplate.

h) Continue adjusting the jackscrews or shims and

tightening the anchor bolts until the baseplate is
level.

i)

Check initial alignment. If the pump and motor
were removed from the baseplate proceed with
step j) first, then the pump and motor should be
reinstalled onto the baseplate using Flowserve’s
factory preliminary alignment procedure as
described in section 4.5, and then continue with
the following. As described above, pumps are
given a preliminary alignment at the factory. This
preliminary alignment is done in a way that ensures
that, if the installer duplicates the factory conditions,
there will be sufficient clearance between the motor
hold down bolts and motor foot holes to move the
motor into final alignment. If the pump and motor
were properly reinstalled to the baseplate or if they
were not removed from the baseplate and there has
been no transit damage, and also if the above steps
where done properly, the pump and driver should
be within 0.38 mm (0.015 in.) FIM (Full Indicator
Movement) parallel, and 0.0025 mm/mm (0.0025
in./in.) FIM angular. If this is not the case, first
check to see if the driver mounting fasteners are
centered in the driver feet holes. If not, re-center
the fasteners and perform a preliminary alignment
to the above tolerances by shimming under the
motor for vertical alignment, and by moving the
pump for horizontal alignment.

j)

Grout the baseplate. A non-shrinking grout
should be used. Make sure that the grout fills the
area under the baseplate. After the grout has
cured, check for voids and repair them.
Jackscrews, shims and wedges should be
removed from under the baseplate at this time. If
they were to be left in place, they could rust,
swell, and cause distortion in the baseplate.

k) Run piping to the suction and discharge of the

pump. There should be no piping loads
transmitted to the pump after connection is made.
Recheck the alignment to verify that there are no
significant loads.

4.5 Initial alignment


4.5.1 Horizontal initial alignment procedure
The purpose of factory alignment is to ensure that the
user will have full utilization of the clearance in the
motor holes for final job-site alignment. To achieve
this, the factory alignment procedure specifies that
the pump be aligned in the horizontal plane to the
motor, with the motor foot bolts centered in the motor
holes. This procedure ensures that there is sufficient
clearance in the motor holes for the customer to field
align the motor to the pump, to zero tolerance. This
philosophy requires that the customer be able to
place the base in the same condition as the factory.
Thus the factory alignment will be done with the base
sitting in an unrestrained condition on a flat and level
surface. This standard also emphasizes the need to
ensure the shaft spacing is adequate to accept the
specified coupling spacer.

The factory alignment procedure is summarized below:
a) The baseplate is placed on a flat and level

workbench in a free and unstressed position.

b) The baseplate is levelled as necessary. Levelling

is accomplished by placing shims under the rails
of the base at the appropriate anchor bolt hole
locations. Levelness is checked in both the
longitudinal and lateral directions.

c) The motor and appropriate motor mounting

hardware is placed on the baseplate and the
motor is checked for any planar soft-foot
condition. If any is present it is eliminated by
shimming.

d) The motor feet holes are centered on the motor

mounting fasteners. This is done by using a
centering nut as shown in Figure 4-6.

Figure 4-6

e) The motor is fastened in place by tightening the

nuts on two diagonal motor mounting studs.

f) The pump is put onto the baseplate and levelled.

The foot piece under the bearing housing is
adjustable. It is used to level the pump, if necessary.
If an adjustment is necessary, add or remove
shims [3126.1] between the foot piece and the
bearing housing.

g) The spacer coupling gap is verified.

Advertising