GE SG SERIES 20 User Manual

Page 50

Advertising
background image

g

GE

OPM_SGS_USM_10K_40K_0US_V010.doc

50/88 Operating

Manual

SG Series 10, 20, 30 & 40 kVA

7.2.2 Complete UPS shutdown (No Load supply)

The Load must be disconnected.

Initial status:
Load supplied from Inverter.

1. Press total off button.

Load is disconnected from UPS.

Rectifier is shut down and all output and
input contactors will be opened.

LED’s, Rectifier, Inverter and Load are
OFF.

2. Open Q1 (Pos. O).

LED service check lights up.

3. Disconnect the Battery from the UPS

in case of External Battery.

Wait 5 minutes for DC-Link Capacitors
discharge.

4. Disconnect the Utility.

All LED’s are OFF.

End of procedure

Advertising
This manual is related to the following products: