7.2.3 Restore to normal operation after “total off”

View of the panel after pressing the
button “total off”
.

All Contacts are open;

Rectifier, Inverter and Static-Switch
shutdown.

1. Reset total off by pressing and

holding the “total offbutton and the
inverter on ( I ) key simultaneously
until the Rectifier starts.

2. Connect the Battery to the UPS by closing the Battery Switch or Fuses, in case

of External Battery.

3. Press inverter on ( I ) key.

Soft-start of Inverter indicated with
blinking LED.

At the end of Soft-start the LED
remains lit.

UPS output LED indicates Load on
Inverter
.

The LCD must display on the main screen the status LOAD ON INVERTER.

End of procedure