14 e1/t1 installation guide, 1 preparing the ptp 600 series bridge e1/t1 cable, E1/t1 installation guide – Motorola MotoWI4 PTP 600 Series User Manual
Page 193: Preparing the ptp 600 series bridge e1/t1 cable, Figure 111 - completed odu connector
Advertising
191
14 E1/T1
Installation
Guide
14.1 Preparing the PTP 600 Series Bridge E1/T1 Cable
Note: The maximum cable length between the ODU and the customers terminating
equipment is 200m (656 feet) for T1.
The E1/T1 cable should be assembled to the following instructions:
Step 1: Assemble gland on cable as shown
Step 2: Strip the outer insulation
Step 3: Arrange conductors as shown in fig.
A2 and cut to length
Step 4: Insert conductors and crimp
Figure 111 - Completed ODU Connector
Advertising