3.6 UNPACKING


Move the equipment in it’s original packing, carton box or wooden case, until the place of installation
and remove the packing and the transport sockets only just before installing the UPS.

1

Procedure for the unpacking of the UPS:

• Make sure to have sufficient space around the UPS

before you start unpacking.

• Cut the two straps A fixing the carton box.

2

• Remove the wooden top cover B, which will be used

as a ramp and position it as shown in the picture.

• Remove the protection Coutside the cabinet and the

accessories bag.

• Remove the carton box D.

3

• Remove the 3 angle irons E”, which are fixing the UPS

to the wooden base G by unscrewing bolts F.

4

• Push now the UPS towards the ramp B and let it

slide down the ramp.
This has to done with the utmost care!

Fig. 3.6-1

LP 33U Series unpacking sequence

NOTE !

Be aware of the heavy weight of the UPS, in
particular if already equipped with
Batteries.