Chapter 6
Performance Verification
Procedure

6-1

INTRODUCTION

The following are the specific tests that should be used to verify the per-
formance of the Power Amplifier Test System (PATS)

q

Source Output Level Accuracy Test

q

Return Loss Measurement Confidence Test

q

System Dynamic Range Test

q

Receiver Magnitude Display Linearity Test

6-2

CONVENTIONS

In the tests in this chapter, instructions will direct use front panel hard
keys and softkeys. The hard keys and softkeys will appear in a different
typeface. For example:

Step 1.

Press the

Utility

key and select:

DIAGNOSTICS

TROUBLESHOOTING

MORE

VERIFY ALC CALIBRATON

The

Utility

key is a front panel hard key and

DIAGNOSTICS, TROUBLE-

SHOOTING, MORE, and VERIFY ALS CALIBRATION

are all softkeys.

6-3

TEST
EQUIPMENT

The following equipment is required to performthe verification proce-
dures.

q

ANRITSU Model ML243XA Power Meter

q

ANRITSU Model MA247XA Power Sensor

q

ANRITSU Model 3653 or 3753LF N connector Calibration Kit

q

ANRITSU Model SC5237 6 dB Offset Termination

q

ANRITSU Model SC5270 20 dB Offset Termination

q

ANRITSU Model 11N50B Power Divider

q

ANRITSU Model 3670NN50-2 Cable

q

ANRITSU Model 34NN50A Adapter

q

ANRITSU 2100-2 GPIB cable

ME7840A OMM