Upflow installations vent through left--side, See fig. 12), 58h d v – Carrier DIRECT VENT 4 58HDV User Manual

Page 19

Advertising
background image

19

Plastic Cap
Yellow or black

Vent Drain
& Clamps

INLE

T

EXH

A

U

S

T

IN

ON

OFF

VE

NT

Casing Grommet
Black Rubber

5

/

8

(15.9mm) ID

(Loose parts bag)

Drain Connector Black PVC

3

/

4

(19.1mm) PVC X

1

/

2

(12.7mm) CPVC
(Loose parts bag)

Drain Tube
Corrugated

5

/

8

(15.9mm) ID

& Clamps

Coupling & Clamps
(Optional)

25--24--67a

Single Pressure Switch

Dual Pressure Switch Detail

Tee Trap White PVC
(loose parts bag)

2

(50.8mm) PVC

Coupling

On Some Models
ONLY

Rotate downward
5

° to 10°

NOTE: Built--in channel will
be angled 5

° to 10° also.

SIDE VIEW

Either: The PVC
Drain Tee or a field
supplied 2

(50.8mm) PVC Tee

AIR

FL

O

W

AIR

FL

O

W

Relief Tube
Black Rubber

3

/

16

(4.8mm) ID

Drain Tube
Black Rubber

1

/

2

(12.7mm) ID

& Clamps

Representative drawing only, some models may vary in appearance.

Drain Line Vent Tee

3

/

4

(18.1mm) PVC or

1

/

2

(12.7mm) CPVC (Field supplied)

A07707

Fig. 12 -- Upflow Installations Vent through Left Side

Upflow Installations Vent through Left--Side

(See Fig. 12)

Remove drain tee from inducer discharge and remove black drain
tube

1

/

2

″ (12.7mm) ID from bottom of drain tee.

Install Vent Pipe grommet in side of casing.
Cut an appropriate length of 2″ (50.8mm) PVC pipe long enough

to exit the cabinet and connect the vent drain to either:

S

A 2″ (50.8mm) PVC coupling fastened onto the drain tee

Install tee trap into bottom of tee.
Remove knockout from the side of the furnace casing where drain

tube will exit.
Install the

1

/

2

″ (12.7mm) CPVC street elbow on discharge of trap

Install the black PVC drain connector [

3

/

4

″ (19.1mm) PVC x

1

/

2

CPVC from loose parts bag] as shown in the illustration above.

Cut the black drain tube [

5

/

8

″ (15.9mm) ID -- in loose parts bag] to

length to fit between trap and tube connector through grommet.
Clamp both ends of the drain tube using clamps provided.
Glue the CPVC street elbow to the trap using appropriate cleaner

and solvent cement.
Connect the tee trap and the main drain line exiting the casing as
shown in Fig. 12
Note:

It is recommended that all PVC piping and fitting

connections be fit up and inspected before final cementing. Both

the internal trap and the external tee trap must be primed

before operation. Verify all condensate drain connections are
securely clamped. A coupling and clamps (in loose part bag) may

be installed as shown for future servicing of the vent system.

58H