Load cells, J2 j1 – Rice Lake BCi Belt Scale - Installation and Operation Manual Version 2.03 User Manual
Page 34
28
Installation and Operation Manual
Load Cells
To attach the cable from a load cell or junction box to an installed A/D card, route the cable through the cord grip
and ground the shield wire.
Next, remove connector J1 from the single-channel A/D card. The connector plugs into a header on the A/D card.
Wire the load cell cable from the load cell or junction box to connector J1 as shown in the table below.
SIG+
SIG–
SEN+
SEN–
EXC+
EXC–
J1
JP2
JP1
CHANNEL 2
CHANNEL 1
SIG+
SIG–
SEN+
SEN–
EXC+
EXC–
J2
J1
JP3 JP4
JP2
JP1
CH 2
CH 1
Figure 3-2. Single-Channel and Dual-Channel A/D Cards
If using 6-wire load cell cable (with sense wires), remove jumpers JP1 and JP2 before reinstalling connector J1.
For 4-wire installation, leave jumpers JP1 and JP2 on. For 6-wire load cell connections on dual-channel A/D
cards, remove jumpers JP3 and JP4 for connections to J2.
When connections are complete, reinstall load cell connector on the A/D card and use two cable ties to secure the
load cell cable to the inside of the enclosure.
Table 3-1. A/D Card Pin Assignments
A/D Card
Connector Pin
Function
1
+SIG
2
–SIG
3
+SENSE
4
–SENSE
5
+EXC
6
–EXC
•
For 6-wire load cell connections to connector J1, remove jumpers JP1 and JP2.
•
For 6-wire load cell connections to connector J2 (dual A/D cards), remove
jumpers JP3 and JP4.