28

Installation and Operation Manual

Load Cells

To attach the cable from a load cell or junction box to an installed A/D card, route the cable through the cord grip
and ground the shield wire.

Next, remove connector J1 from the single-channel A/D card. The connector plugs into a header on the A/D card.
Wire the load cell cable from the load cell or junction box to connector J1 as shown in the table below.

SIG+

SIG–

SEN+

SEN–

EXC+

EXC–

J1

JP2

JP1

CHANNEL 2

CHANNEL 1

SIG+

SIG–

SEN+

SEN–

EXC+

EXC–

J2

J1

JP3 JP4

JP2

JP1

CH 2

CH 1

Figure 3-2. Single-Channel and Dual-Channel A/D Cards

If using 6-wire load cell cable (with sense wires), remove jumpers JP1 and JP2 before reinstalling connector J1.
For 4-wire installation, leave jumpers JP1 and JP2 on. For 6-wire load cell connections on dual-channel A/D
cards, remove jumpers JP3 and JP4 for connections to J2.

When connections are complete, reinstall load cell connector on the A/D card and use two cable ties to secure the
load cell cable to the inside of the enclosure.

Table 3-1. A/D Card Pin Assignments

A/D Card

Connector Pin

Function

1

+SIG

2

–SIG

3

+SENSE

4

–SENSE

5

+EXC

6

–EXC

For 6-wire load cell connections to connector J1, remove jumpers JP1 and JP2.

For 6-wire load cell connections to connector J2 (dual A/D cards), remove

jumpers JP3 and JP4.