Installation & Operation Manual - Calibration

53

Simulated Testing

A simulated load test consisting of at least three consecutive test runs should be conducted as soon as possible,
but not more than 12 hours after the completion of the material test, to establish the factor to relate the results of
the simulated load test to the results of the material tests. The results of the simulated load test should repeat
within 0.1 percent.

Simulated testing is used only with auto calibration of the integrator.

There are two different simulated load testing techniques that can be used. They are:

Roller test chains

Static test weights

There are several advantages and disadvantages to each of the list simulated testing techniques. They are listed
below.

Table 5-2. Advantages and Disadvantages to Simulated Testing

Simulated Testing Type

Advantages

Disadvantages

Roller (chain)

Simulates some conveyor belt
effects

Chains do not provide a traceable
conveyor scale calibration
standard.

Acceptable simulated test

Heavy chains are difficult to
handle.
Conveyor belt must be stopped
to apply and remove.
Linearity test requires several
chains.
Chains are costly.

Static

Test Weights (3)

Belt Scale

Test Weight Brackets

Simulates some conveyor belt
effects

Weights do not provide a
traceable conveyor scale
calibration standard

Easy to apply

Does not simulate conveyor belt
effects

Conveyor belt does not have to
be stopped to apply
Linearity test is easy to perform
Detect load cell failures, and
applies force to the load cell
Acceptable simulated test