CB-2 Automated Concrete Batching System Installation/Operation Manual

5. Apply the test weights to the scale. Press the

Calibrate Span

button to perform the span

calibration (see Figure 5-7). A message box

appears when the process is complete.

Figure 5-7. iRev Span Calibration Display

6. If the option for chains or hooks was selected

in step 3, the Rezero display is shown (see

Figure 5-8). Remove all weights from the

scale, including chains or hooks. Press the

Re-Zero

button to calibrate the zero offset.

Figure 5-8. iRev Rezero Display

7. If performing a multi-point linear calibration,

up to five other calibration weight values can

be entered on the display shown in Figure 5-9.

The weights must be in ascending order and

must not include zero or the span weight.

Enter the weight values and click the

Go

button to calibrate each point.

Figure 5-9. iRev Linear Calibration Display

8. Review the new calibration values then click

Finish

to close the Calibration Wizard. To

restore the current calibration values, click

Cancel

.

Figure 5-10. iRev Calibration Values Display