Wiring the housing board

To wire the housing board, do the following:

1. Connect the facility data cables to the main connections, which are the B and A terminals on the

provided 6-pin or 2-pin terminal strip (Figure 19). The main data connections on the terminal strip are
for control wires that are coming in from the keypad. You may also daisy-chain the data signal to
additional domes.

Note: If you are installing RS-485 data, float the shield at the dome and connect it at the keypad.

Figure 19. Data connections

2. Connect the facility video cable (Figure 20).

Note: Use only crimp-on BNC connectors. Do not use screw-on connectors.

Figure 20. Video connection

If you are installing UTP video, use the UTP terminals on the six-pin terminal strip. It provides
connections for UTP video. If you are installing coaxial video, locate the BNC connector.

Note: UTP, which is polarity sensitive, is only available on standard modules with a six-pin connector.

WARNING: Do not run any cables next to the heaters. Doing so could damage the dome or cause an electrical fire.

B A B A

Primary A
RS-485 +

Auxiliary B

RS-485 –

Primary B
RS-485 –

Auxiliary A

RS-485 +

Coaxial video

BNC