9 - GAS SUPPLY PIPING

CAUTION

WHAT TO DO IF YOU SMELL GAS

• Do not try to light any appliance.
• Do not touch any electrical switch; do not use

any phone in your building.

• Immediately call your gas supplier from a

neighbor’s phone. Follow gas supplier’s

instructions.

• If you cannot reach your gas supplier, call the fire

department.

!

9.1 Check Gas Supply

TABLE 6: GAS SUPPLY PRESSURE

Natural Gas

4” min. w.c.

10” max. w.c.

LP Gas

10” min. w.c.

14” max. w.c.

Check line pressure while unit is running in high fire mode.

TABLE 7: GAS PIPING SIZES

Natural Gas

Pipe Length

Pipe Capacity - BTU/Hr. Input Includes Fittings

½”

¾”

1”

1¼”

20’

92,000

190,000

350,000

625,000

40’

63,000

130,000

245,000

445,000

60’

50,000

105,000

195,000

365,000

LP Gas

Pipe Length

Pipe Capacity - BTU/Hr. Input Includes Fittings
Copper Tubing (O.D.)

Iron Pipe

⅝”

¾”

½”

¾”

20’

131,000

216,000

189,000

393,000

40’

90,000

145,000

129,000

267,000

60’

72,000

121,000

103,000

217,000

The length of pipe or tubing should be measured from the gas meter or

propane second stage regulator.

• Gas pipe to boiler must be correct size for length of

run and total Btuh input of all gas utilization equipment

connected to it. See Table 7 for proper size.

• Verify your gas line complies with local codes and gas

company requirements.

• Disconnect boiler and its individual shutoff valve from

gas supply piping system during any pressure testing of

system at test pressures in excess of ½ psig (3.5kPa).

• Isolate boiler from gas supply piping system by closing

its manual shutoff valve during any pressure testing of

gas supply piping system at test pressures equal to or

less than ½ psig (3.5kPa).

• For proper boiler operation line pressure should be

within minimum and maximum values in Table 6.

• Gas line enters boiler through left side panel. See page

2 Dimensions and Figure 10.

Boiler is equipped with ½” NPT connection on gas valve for

supply piping and ½” NPT ball valve for manual shut off.

Following rules apply:

1.

Use only those piping materials and joining methods

listed as acceptable by the authority having jurisdiction,

or in the absence of such requirements,

• United States - National Fuel Gas Code, ANSI

Z223.1/NFPA 54.

• Canada - Natural Gas and Propane Installation Code,

CAN/CSA B149.1.

2.

Use pipe joint compound suitable for liquefied

petroleum gas on male threads only.

3.

Refer to Figure 10 for general layout, which shows

basic fittings needed. As shipped, gas line enters

boiler through right side, as an option, it can be routed

through either rear or left side panel.

4.

Use ground joint unions.

5.

Install sediment trap upstream of gas controls.

6.

Use two pipe wrenches when making connection to the

gas valve to keep it from turning.

7.

Install manual shutoff valve in vertical pipe about 5’

above floor outside boiler jacket in addition to shutoff

valve supplied with boiler.

8.

Tighten all joints securely.

9.

Propane gas connections should only be made by

licensed propane installer.

10.

Two stage regulation should be used by propane

installer.

11.

Propane gas piping should be checked by propane

installer.

9.2 Connecting Gas Piping