Power up, Instant-on – Altera MAX 10 FPGA User Manual

Page 28

Advertising
background image

Related Information

.pof Generation through Convert Programming Files

on page 3-6

Provides more information about how to set th weak pull-up during configuration.

Power Up

If you power-up a device from the power-down state, you need to power the V

CCIO

for bank 1B and 8 to

the appropriate level for the device to exit POR.
To begin configuration, the required voltages must be powered up to the appropriate voltage levels as

shown in the following table. The V

CCIO

for bank 1B and bank 8 must be powered up to a voltage between

1.5V – 3.3V during configuration.

Table 2-19: Single-Supply and Dual-Supply Voltage Requirements for MAX 10 Devices

Power Supply Device Options

Voltage that must be Powered-Up

Single-supply

Regulated V

CC_ONE

V

CCA

V

CCIO

bank 1B and bank 8

Dual-supply

V

CC

V

CCA

V

CCIO

bank 1B and bank 8

Related Information

MAX 10 Power Management User Guide

Provides more information about power supply modes in MAX 10 devices

MAX 10 Device Datasheet

Provides more information about the ramp-up time specifications.

MAX 10 FPGA Device Family Pin Connection Guideline

Provides more information about configuration pin connections.

Instant-on

The MAX 10 devices support instant-on feature. The instant-on mode is the fastest power-up mode for

MAX 10 devices.
If you enable instant-on, the device will directly enter the configuration stage. The POR delay value will be

used to delay the POR signal if the instant-on feature is not enabled.

Table 2-20: Instant-On Power Up Sequence Requirement for MAX 10 Devices

Power Supply Device Options

Power Up Sequence

Single-supply

V

CCIO

must ramp up to full rail before V

CCA

and V

CC_ONE

start ramping

Dual-supply

All power supplies must ramp up to full rail before V

CC

starts ramping

2-24

Power Up

UG-M10CONFIG

2015.05.04

Altera Corporation

MAX 10 FPGA Configuration Schemes and Features

Send Feedback

Advertising