Auto Calibration Setup

The automatic calibration feature allows the instrument to calibrate itself using external supplies of zero

and span calibration gases at pre-determined intervals or events as dictated by the user. The first step

when setting up the automatic calibration feature on the MGA 6010 is to connect the Zero and Span

calibration gases to the appropriate ports on the left side of the enclosure. There are blocking solenoids

at each of these ports to only allow the flow of gas when it is called for and to prevent the flow when not

needed. The pressure in the gas lines will need to be adjusted to maintain a flow rate similar to the

sample flow rate, which should be between 20 and 50psi.

Method #1: Automatic calibrations based on timed intervals

The interval between calibrations is determined on the Auto Calibration Setup screen. Auto Calibration

must be set to “On”. The calibration purge timer allows for the flow of calibration gas to purge the

sample gas from the instrument before performing a calibration. If the sample lines are long the time

can be increased from the default value of 90 seconds.

The zero and span intervals are measured in hours. The appropriate interval can be based on the

process and the desired degree of accuracy. The standard values are 48 hours for a zero calibration and

96 hours for a span calibration.

Method #2: Automatic calibration based on digital inputs

It is also possible to initiate calibrations externally. This method may be beneficial if the calibration is to

be tied in with a process event or as directed by a PLC. Connecting Terminals 2351 and the adjacent GND

terminal will initiate an automatic Zero calibration. Connecting Terminals 2331 and the adjacent GND

terminal will initiate an automatic Span calibration. Calibration can be initiated using the digital inputs

regardless of the timed interval calibration setup. There are no setups required for the digital inputs

since they are not user-configurable.

The three buttons at the bottom of the screen (Zero Calibration, Span Calibration, Zero and Span

Calibration), can be used to initiate immediate calibrations from the Auto Calibration Setup screen.

These buttons will not work unless the automatic calibration feature has been enabled.