Config Pri : 100 Running Pri : 100

Preempt Mode : Yes Delay Time : 0

Auth Type : None

Virtual IP : 192.168.0.10

Virtual MAC : 0000-5e00-0101

Master IP : 192.168.0.102

The above output indicates that when Switch A detects that the uplink fails through BFD, it decreases

its priority by 20 to ensure that Switch B can preempt as the master.

Static Routing-Track-NQA Collaboration Configuration Example

Network requirements

As shown in

Figure 12-5

, Switch A, Switch B, Switch C, and Switch D are connected to two segments

20.1.1.0/24 and 30.1.1.0/24. Configure static routes on these switches so that the two segments can

communicate with each other, and configure route backup to improve reliability of the network.

Switch A is the default gateway of the hosts in segment 20.1.1.0/24. Two static routes to 30.1.1.0/24

exist on Switch A, with the next hop being Switch B and Switch C respectively. These two static routes

back up each other, where:

z

The static route with Switch B as the next hop has a higher priority, and is the master route. If this

route is available, Switch A forwards packets to 30.1.1.0/24 through Switch B.

z

The static route with Switch C as the next hop acts as the backup route.

z

Configure static routing-track-NQA collaboration to determine whether the master route is

available in real time. If the master route is unavailable, the backup route takes effect, and Switch

A forwards packets to 30.1.1.0/24 through Switch C.

Similarly, Switch D is the default gateway of the hosts in segment 30.1.1.0/24. Two static routes to

20.1.1.0/24 exist on Switch D, with the next hop being Switch B and Switch C respectively. These two

static routes back up each other, where:

z

The static route with Switch B as the next hop has a higher priority, and is the master route. If this

route is available, Switch D forwards packets to 20.1.1.0/24 through Switch B.

z

The static route with Switch C as the next hop acts as the backup route.

z

Configure static routing-track-NQA collaboration to determine whether the master route is

available in real time. If the master route is unavailable, the backup route takes effect, and Switch

D forwards packets to 20.1.1.0/24 through Switch C.

Advertising
This manual is related to the following products: