Checklist before installation

Table 5 Checklist before installation

Item Requirements

Result

Installation site

Weight support

The floor can support the total weight of the chassis and
all other components.

Temperature

0°C to 45°C (32°F to 113°F)

Relative humidity

10% to 95% (noncondensing)

Cleanness

Dust concentration ≤ 3 × 10

4

particles/m

3

No dust on desk within three days

Ventilation

There is a minimum clearance of 10 cm (3.94 in)
around the inlet and exhaust vents for heat

dissipation of the firewall chassis.

A ventilation system is available at the installation

site.

ESD prevention

The equipment and floor are well grounded.

The equipment room is dust-proof. An anti-static floor

is installed and properly grounded.

The humidity and temperature are at a proper level.

Wear an ESD-preventive wrist strap and uniform

when touching a circuit board.

Place the removed CF card and interface modules on

an anti-static workbench, with the face upward, or
put it into an anti-static bag.

Touch only the edges, instead of electronic
components when observing or moving a removed

CF card or interface module.

 