Installing the firewall, Confirming installation preparations – H3C Technologies H3C SecPath F1000-E User Manual

Page 22

Advertising
background image

14

Installing the firewall

Figure 13 Firewall installation flow

Confirming installation preparations

Before you install the firewall, verify that:

You have read "

Preparing for installation

" carefully and the installation site meets all the

requirements.

A 19-inch rack is ready for use.

The rack is sturdy and securely grounded.

There is sufficient clearance around the rack for heat dissipation and installation.

No debris exists inside or around the rack.

Choose a correct rack mounting position for the firewall. Make sure the heaviest device is placed
at the bottom of the rack.

Advertising