Emerson 7400 User Manual

Page 32

Advertising
background image

23

Series 7400 Single Phase 1+N UPS

In 25kVA to 125 kVA module installations the batteries associated

with the UPS equipment are usually contained in a purpose-built
battery cabinet/ rack which sits alongside the main UPS equipment.

Sealed, maintenance-free batteries are normally used in this type

of installation.


Due to their increased capacity, the batteries associated with

larger UPS installations are usually too big to be mounted in a

single cabinet and are either rack mounted or fitted in multiple, or
bespoke, battery cabinets. Such installations may utilise non-

sealed lead acid cells, requiring regular attention and impose their

own environmental requirements.


Pedestals are required for the battery cabinets when they are

located on raised floors, in the same way as for the UPS cabinets.


Where battery racks are used, they should be sited and assembled

in accordance with the battery manufacturer’s recommendations.

In general, batteries require a well ventilated, clean and dry
environment at reasonable temperatures to obtain efficient battery

operation.

Battery manufacturers’ literature provide detailed safety measures
to be observed when employing large battery banks and these

should be studied and the proposed battery installation checked to

verify compliance with the appropriate recommendations.

The batteries are connected to the UPS through a circuit breaker

which is manually closed and electronically tripped via the UPS

control circuitry. If the batteries are cabinet-mounted this circuit
breaker is fitted within the cabinet; however, if the batteries are

rack-mounted or otherwise located remote to the main UPS

cabinet then the battery circuit breaker must be mounted as near
as possible to the batteries themselves, and the power and control

cables connected to the UPS using the most direct route possible.

Emerson Network Power (India) Pvt. Ltd. offer a purpose-designed

remote battery circuit breaker box, containing the circuit breaker
and its necessary control board, as a standard option kit.

3.2 Preliminary Checks

Before you install the UPS hardware you should carry out the

following preliminary checks:

1. Verify that the UPS room satisfies the environmental conditions

stipulated in the equipment specification, paying particular
attention to the ambient temperature and air exchange system.

2. Remove any packaging devices debris then visually examine

the UPS and battery equipment for transit damage, both
internally and externally. Report any such damage to the

shipper immediately.


3. Verify that the shipment is complete -e.g. that the battery

contains the correct number of cells etc. Report any

discrepancy immediately.


4. When you are satisfied that the equipment is complete and in

good condition move it to its proposed final position.

3.1.3 Battery Location

Advertising