Series 7400 Single Phase 1+N UPS

A N N E X U R E

Inter Connection cable details
Any system essentially needs UPS module. However many

customers need auxiliary cubicles such as Input Isolation

Transformers, Battery Current Sharing Kit, 1+1 Paralleling kit,

Bypass SCVS / SVR or Bypass Line Transformers. In case any of
the auxiliary cubicle or combination of them is required & ordered

by the customer, we would like to recommend following sequence

in which the cubicles shall be located.

SCVS

or

SVR

TXR

Cubicle 1


UPS 1

UPS 2

TXR

Cubicle 2

or

Battery

Sharing Kit

It should be noted that this is the recommended panel line up &
based on this line up we will provide all interconnection cables. The

interconnecting cables are supplied only if auxiliaries are in ENP’s

scope. ENP is not responsible for supply of these interconnection

cables in case the recommended Line up is altered. It is presumed
that

a)

All the panels are in single line up.

b)

All the panels are placed in such a way that side covers are

touching to each other.

c)

Location of UPS panels remain unchanged.

d)

In case any of the panel is not ordered its left hand side

panel shall be shifted to ensure no gap between UPS &

other panels i.e. in case Transformer Cubicle is not required

the SCVS or SVR will be placed at the location of
Transformer Cubicle.

We are enclosing the typical interconnection diagram which will
remain unchanged for all permutations & combinations of various

options.