Installing a rack, Preinstallation activities, Site plan verification – Intel SGI Altix 450 User Manual

Page 28

Advertising
background image

6

007-4857-002

1: System Installation

Installing a Rack

This section describes how to install a rack that already has your system IRUs rackmounted and
cabled together. The following information is provided:

“Preinstallation Activities” on page 6

“Unloading and Moving System Equipment” on page 12

“Removing a Short Rack from the Shipping Crate” on page 16

“Unpacking and Installing the Tall Rack” on page 18

“Positioning and Leveling Racks” on page 21

After you have completed installing your rack, proceed to “Cabling the System IRUs to a Power
Source” on page 31 to cont
inue your installation.

If your system components were not shipped in a rack, skip this section and proceed to
“Unpacking and Inspecting Modules” on page 22 to begin your installation.

Preinstallation Activities

Perform the following preinstallation activities:

Perform site verifications (see “Site Plan Verification” on page 6)

Gather appropriate tools to complete the installation (see “Tools Required” on page 7)

Ensure that the correct power receptacle is installed and properly wired (see “Power
Receptacle Verification” on page 8)

Note: You can perform the preinstallation activities days or weeks before you receive your
system.

Site Plan Verification

Ensure that all site requirements are met before your system arrives. If you have questions about
the site requirements or you would like to order full-size floor templates for your site, contact a
site planning representative by e-mail ([email protected]).

Advertising