Chapter 5, Prepare for router installation – Juniper Networks M5 User Manual

Page 57

Advertising
background image

Chapter 5

Prepare for Router Installation

This chapter describes how to prepare your site for installation of the M5 and M10 Internet
routers. It discusses the following topics:

•

Rack Requirements on page 37

•

Clearance Requirements for Airflow and Hardware Maintenance on page 40

•

Router Environmental Tolerances on page 40

•

Fire Safety Requirements on page 41

•

Power Guidelines, Requirements, and Specifications on page 42

•

Network Cable Specifications and Guidelines on page 48

•

Cable Specifications for Routing Engine Management Interfaces on page 52

•

Site Preparation Checklist on page 52

Rack Requirements

The router must be installed in a rack. Many types of racks are acceptable, including
front-mount racks, 4-post (telco) racks, and center-mount racks. An example of a
center-mount rack appears in Figure 16.

The following sections describe rack requirements:

•

Rack Size and Strength on page 37

•

Spacing of Mounting Holes on page 39

•

Connection to Building Structure on page 39

Rack Size and Strength

The router is designed for installation in a rack that complies with either of the following
standards:

•

A 19-in. rack as defined in Cabinets, Racks, Panels, and Associated Equipment
(document number EIA-310-D) published by the Electronics Industry Association
(http://www.eia.org).

Prepare for Router Installation

37

Advertising
This manual is related to the following products: