4. Assembly

PNEG-1445 6", 8", 10" and 12" Custom Augers

31

Basic Inlet Hoppers

1. Follow the cutting guidelines

on Page 29

.

2. Attach hoppers to tube as shown

in Figure 4AE

.

3. Follow the instructions below before cutting and installing inlet hopper.

a. Slide ring flange onto the end of tube and weld, making sure the flange is mounted squarely.

b. Bolt end plate to flange.

c. Bolt bearing to end plate.

d. Guide intake stub through bearing and tighten the lock collar.

e. Install any covers if applicable.

Figure 4AE

Spouting, Fittings and Truss Kits

Spouting and Fittings

To connect sections of spouting or to connect fittings to spouting, use one or all of the following procedures:

1. Spouting to Spouting - Slide flange rings over ends of spouting to be joined and weld in place. Make

sure flanges are mounted squarely. Join flanges and bolt together.

2. Spouting to Fitting - Install ring flange on spouting as in

Step 1

. Join to flange on fitting (valve,

dead head, slip joints, etc.)

3. Flange Clamps - Fit each half over flanges and tighten with bolts provided.

4. Quick Connect Flange Clamps - Fit each half over flange and tighten bolt. Do not use in location

where permanent unions are required.