Piping – Xylem IM191 R03 Marlow Series Prime Line Self-Priming Centrifugal Pumps User Manual

Page 5

Advertising
background image

5

Figure 5

Figure 6

H min.

D

D

H min.

D

D

1.5D

min.

3.0D
min.

H min.

D min.

2

16

15

14

13

12

11

10

9

8

7

6

5

4

3

2

1

H = Min. Submergence in feet

H

1 2 3 4 5 6 7 8 9 10111213141516

V

V = Velocity in feet per second

= GPM x 0.321

Area

GPM x 0.4085

D

2

Figure 3

Figure 4

FRAME-MOUNTED UNITS ONLY
• Alignment MUST be checked prior to running. See Figure 2.

Figure 2

• Tighten all hold-down bolts before checking alignment.
• If realignment is necessary, always move the motor. Shim

as required.

• Parallel misalignment, shafts with axis parallel but not

concentric. Place dial indicator on one hub and rotate this

hub 360° while taking readings on the outside diameter of

the other hub. Parallel alignment is achieved when reading is

0.010" (0.254 mm) TIR, or less.

• Angular misalignment, shaft with axis concentric but not

parallel. Place dial indicator on one hub and rotate this hub

360° while taking readings on the face of the other hub.

Angular alignment is achieved when reading is 0.020"

(0.508 mm) TIR, or less.

• Final alignment is achieved when parallel and angular re-

quirements are satisfied with motor hold-down bolts tight.

NOTICE: ALWAYS RECHECK BOTH ALIGNMENTS

AFTER MAKING ANY MECHANICAL

ADJUSTMENTS.

Piping

• Piping should be no smaller than pump’s discharge and

suction connections and kept as short as possible, avoiding

unnecessary fittings to minimize friction losses.

• All piping MUST be independently supported and MUST

NOT place any piping loads on the pump

NOTICE: DO NOT FORCE PIPING INTO PLACE

AT PUMP SUCTION AND DISCHARGE

CONNECTIONS.
• All pipe joints MUST be airtight.
PIPING – SUCTION
• For suction lifts over 10 ft. (3 m) and liquid temperatures

over 120° F (49° C), consult pump performance curve for

net positive suction head required (NPSH

R

).

• If a pipe size larger than pump suction is required, an ec-

centric pipe reducer, with the straight side up, MUST be

installed at the pump suction.

• If pump is installed below the liquid source, install a gate

valve in the suction for pump inspection and maintenance.

NOTICE: DO NOT USE THE GATE VALVE TO

THROTTLE PUMP. THIS MAY CAUSE LOSS

OF PRIME, EXCESSIVE TEMPERATURES

AND DAMAGE TO PUMP, VOIDING

WARRANTY.
• If the pump is installed above the liquid source, the following

MUST be provided:

• To avoid air pockets, no part of the piping should be above

the pump suction connection.

• Slope the piping upward from liquid source.

• Use a foot valve or check valve ONLY if necessary for

priming or to hold prime during intermittent duty.

• The suction strainer or suction bell MUST be at least

3 times the suction pipe diameter area.

• Insure that the size and minimum submergence over suc-

tion inlet is sufficient to prevent air from entering pump

through a suction vortex. See Figures 3 through 6.

PIPING – DISCHARGE
• Install a check valve suitable to handle the flow, liquids and

to prevent backflow. After the check valve, install an ap-

propriately sized gate valve to be used to regulate the pump

capacity, pump inspection and for maintenance.

• When required, pipe increaser should be installed between

the check valve and the pump discharge.

AIR RELEASE LINE (4E & 6E)
It is essential to allow the air to escape from the discharge

line to atmosphere during the initial priming and re-priming

cycle. In systems with high discharge heads, it may be advisable

to install an air release line between the pump casing and

discharge check valve to aid their venting. The size of the

air release line is selected such that it does not significantly

affect the discharge capacity. You may install an air release line

through the filler plug hole if necessary. However, the preferred

location is in the discharge line – between the pump and the

discharge check valve – as close to the discharge check valve

as possible. We recommend the following line sizes for the

following pumps:

4" pump – ¾" line

6" pump – 1" line
NOTES:

1. This line size may be increased or decreased depending on

application.
2. Direct the air release line back into the sump (not into

the pump suction line). Leave the end of the line open to

atmosphere. Do not submerge into the liquid being

pumped.
3. The air release line may clog, particularly if a shut-off

valve is installed in the line and is closed during operation.

If this condition occurs, either use a larger line or leave the

shut-off valve open during pumping operation. To aid in

maintaining air release lines, fit them with crosses

instead of elbows.

Parallel

Angular

Advertising