Installation

15. Drill the holes in the floor using a drill with an 8Ø bit and fit the expandable bolts provided as indicated in the

drawing and tighten them to a torque of 25 Nm. As indicated in the box, in the last phase, fasten the mounting

brackets on the side of the column and tighten to a torque of 25Nm (15) .

16. Check that the mains input voltage and frequency

parameters are compatible with the data shown on

the wheel balancing machine plate (±10%) (16).

17. Check proper pneumatic connection; the machine and

the lift require at least 8 kg/cm² (~ 0.8 MPa; ~8 BAR;

~115 PSI) (17).

18. Turn on the machine and carry out the following

operations:

LASER CALIBRATION

TAPER CALIBRATION

MACHINE CALIBRATION