16

LC Series chillers have factory installed

louvered sheet metal condenser coil guards.

The placement relative to the building air

intakes and other structures must be

carefully selected. Airflow to and from the

chiller must not be restricted to prevent a

decrease in performance and efficiency.

The installation position must provide at

least 3 feet of side clearance for proper

airflow to the condenser coils. When units

are mounted adjacent to each other, the

minimum clearance required between the

units is 6 feet

Units should not be installed in an enclosure

or pit that is deeper than the height of the

unit. When recessed installation is

necessary, the clearance to maintain proper

airflow is at least 6 feet.

LC Series chillers have a vertical air

discharge. There must be no obstruction

above the equipment. Do not place the unit

under an overhang.

For proper unit operation, the immediate

area around condenser must remain free of

debris that may be drawn in and obstruct

airflow in the condensing section.

Consideration must be given to obstruction

caused by snow accumulation when placing

the unit.

Water Connection

Connect the chiller supply and return water

lines. The connection size is listed on the

unit rating sheet, along with the designed

volumetric flow rate. The maximum

operating pressure for the AAON LC Series

chiller is 125 psi.

Mounting Isolation

For roof mounted applications or anytime

vibration transmission is a factor, vibration

isolators may be used.

Access Doors

Access doors are provided to the compressor

and electrical compartment. A separate

access door is also provided to the

evaporator/heat exchanger compartment.

Low Ambient Operation

During low ambient temperatures, it is

difficult to start a system because the

refrigerant will migrate to the cold part of

the system (condenser) and make it difficult

for refrigerant to flow. All chiller

compressors are provided with factory

installed crankcase heaters. The LC Series

chiller must have continuous power 24 hours

prior to startup. This ensures the compressor

will receive sufficient refrigerant vapor at

startup.

The chiller must be operated with

liquid flowing through the

evaporators.

WARNING

PVC (Polyvinyl Chloride) and CPVC

(Chlorinated Polyvinyl Chloride) are

vulnerable to attack by certain

chemicals. Polyolester (POE) oils

used with R-410A and other

refrigerants, even in trace amounts,

in a PVC or CPVC piping system will

result in stress cracking of the piping

and fittings and complete piping

system failure.

CAUTION