Nova-Tech LMI Series AA-B-C-E-J-P Metering Pumps User Manual

Page 37

Advertising
background image

37

IMPORTANT:Notecorrectorientationofeachcheckvalve.

5. Install the new spring in the Injection Check Valve.



Depressurize and drain pipeline (or isolate I.C.V. point using

valves) so that I.C.V. can safely be disassembled.

10.0 Checking Pump for Proper Zero Position

(Stroke Knob)

1. With pump running, turn stroke knob counter-clockwise

toward zero or end of black or red band on dial.

2. LISTEN to the clicking as the pump is running. The pump

should operate quietly at the zero position (no clicking).

3. If the pump continues to click at zero or stops clicking before

zero is reached, the pump zero must be reset (see Section

10.1 or 10.2).

10.1 Type I - Push on Knob

Re-Zeroing and Stroke Knob

Disassembly and Assembly


`

1. Remove stroke knob from the pump by grasping the knob

firmly and pulling it toward you.

2. Pry off the yellow cap.

3. Place the knob on a flat surface.

4. Using needle-nose pliers, squeeze the inner section together

while lifting the outer section up.

5. Push the inner section back onto the “D” shaped stroke

shaft.

6. With the pump running, zero the pump by turning the inner

section of the knob counter-clockwise until the pump

stops clicking.

CAUTION

!