3 changing the process connection, Changing the process connection -2, 3 changing the process con- nection – Yokogawa EJA110A User Manual

Page 23

Advertising
background image

IM 01C21B01-01E

4-2

4 . INSTALLATION

F0403.EPS

Vertical pipe mounting
(Process connector upside)

Vertical pipe mounting
(Process connector downside)

Transmitter
mounting bolt

Transmitter
mounting bolt

Mounting bracket

Mounting bracket

U-bolt nut

U-bolt nut

U-bolt

U-bolt

50 mm(2-inch) pipe

50 mm(2-inch) pipe

Figure 4.2.3 Transmitter Mounting (Vertical Impulse Piping

Type)

4.3 Changing the Process Con-

nection

The transmitter is shipped with the process connection
specified at the time of ordering. To make a change
such as modifying the drain (vent) plug(s) attached to
the upside of the cover flange on shipment to be
attached to the downside follow the procedure below.

To begin, use a wrench to slowly and gently unscrew
the drain (vent) plug(s). Then, remove and remount
them on the opposite side. Wrap sealing tape around
the drain (vent) plug threads (*1 in the figure below),
and apply a lubricant to the threads of the drain (vent)
screw(s) (*2 below) to screw it (them) in. To tighten
the drain (vent) plugs, apply a torque of 34 to 39 N·m
{3.5 to 4 kgf·m}. Tighten the process connector bolts
uniformly to a torque of 39 to 49 N·m {4 to 5 kgf·m}.

F0404.EPS

1

2

Drain/vent plug

Note: For a horizontal impulse

piping type, moving the
process connectors from
the front side to the
back is not allowed.

Vertical impulse piping type

Horizontal impulse piping type

Bolt

Process

connector

gasket

Figure 4.3

Changing Process Connection

Advertising
This manual is related to the following products: