5.1.4 Assembly of VS18/VS26 valve islands

Tools:

VS18:

Hexagon wrench key 2.5mm
Philips screwdriver size 1

VS26:

Hexagon wrench key 3mm
Philips screwdriver size 1


To assemble a complete valve island, make sure you have ordered all necessary components
and the required tools are available.

1. First bolt all modular sub-bases together. Ensure sub-bases are properly aligned and the

gasket is fitted between the sub-bases. Then tighten the mounting screws (two per modular
sub-base) with the specified torque. If you are using a power screwdriver, consider the
maximum speed allowed.

For multi pressure applications, please refer to section

5.1.7

.




Note:

When ordering an even number of stations, please ensure the valve island contains a
maximum of two single station modular sub-bases. E.g.: You order an 8-station Multipole
valve island with an 8-station main PCB. The valve island must have at least three double
station modular sub-bases and must have no more than two single station modular sub-
bases.
When ordering an odd number of stations, the single station modular sub-base should be at
the right end of the valve island. In addition, you can use two additional single station
modular sub-bases, for a total of three.

Screw

Type
(thread)

Valve
seize

Tightening
torque in Nm

Tightening
torque in Ibs

Max. screw driver
speed in r.p.m.

11

M3x10

VS18

0.8 – 0.9

7.08 – 7.96

1100

11

M4x12

VS26

1.0 – 1.1

8.85 – 9.73

1100