5 installation check, Installation check – Lenze ECSDKxxx User Manual
Page 62
Advertising
![background image](/manuals/566107/62/background.png)
Installation check
5
l
62
EDKCSDK002 DE/EN/FR 1.1
5
Installation check
After completing the installation, check ...
ƒ
The wiring for completeness, short circuit and earth fault.
ƒ
The power connection (X23):
–
Polarity of the DC−bus voltage supply via terminals +UG, −UG
ƒ
The control connection (X26):
–
Short−circuiting of charging current limitation depending upon connected
power supply module.
)
Note!
The next step consists of commissioning the drive system.
Relevant information can be found in the detailed documentation of
the connected power supply and axis modules.