3-12

Manual 0-2652

3.12 External Cable Connections

Depending on the options installed there are various cables to
be connected the Power Supply.

A. Optional RC 6010 Remote Control

For mechanized systems, the optional RC 6010 Remote Control
allows the operator to control all system functions from a re-
mote location. The control cable to interface the RC 6010 to the
Power Supply is available in various lengths (Refer to Appen-
dix 4, Typical Mechanized System Cable Interconnection Dia-
gram).

1. Connect the control cable to the receptacle marked RE-

MOTE CONTROL (J15) on the rear panel of the Power
Supply.

A-01765

Cable From

Remote Control

REMOTE

CONTROL J15

Connector

Figure 3-14 Remote Control Interface Connection

2. Connect the other end of the control cable to the re-

ceptacle marked PS (J37) on the rear panel of the re-
mote control.

NOTE

Refer to the RC 6010 Remote Control Instruction
Manual 0-2478 for more information on the
RC6010 Remote Control including CNC.

B. Computer Control Interface (CNC)

NOTE

Used when Remote Control RC6010 or Standoff
Control SC11 are not used.

The computer control interface (CNC) allows a mechanized sys-
tem to interface with a computer or other control device.

NOTE

Refer to Section 4.03-D for more information on
the CNC connections.

CNC cables can be interfaced to the Power Supply using
one of the following methods:

NOTE

Refer to Appendix 7 for CNC Interface Schematic.

• Connector (J15) at the rear of the Power Supply

• Internal terminal strip in the Power Supply

Depending on the equipment ordered and the cables supplied
connect the CNC cable per one of the following:

1. Using supplied CNC cable

Connect the supplied Power Supply/CNC Cable to the
Power Supply rear connector J15 labelled REMOTE
CONTROL.

2. Using customer-supplied CNC Cable

a. Remove the Left Side Panel from the Power Supply

as viewed from the front of the unit.

b. Locate the internal terminal strip (TB2) near the

heatsink.

c. Feed the CNC cable through the small strain relief

at the rear of the Power Supply.

d. Connect the CNC cable to the terminal strip (TB)

per the following chart (see NOTES after chart):