3.5 a. After all pressure plates are installed on the frame, torque FS-325 screws to 90 in-lbs. The use of

either a drill motor with a torque limiter or torque wrench can be used. If using a cordless drill, check

torque periodically since battery usage will affect the torque setting.

b. Install vertical face covers. Using a wood block to protect the cover, apply with dead blow soft face

hammer. Pin the vertical face covers once per length as required, concealing pin at a horizontal

location.

c. Insert backer rod into cavity at the top of each vertical mullion. Seal off end of vertical, sloping sealant

back to marry with the perimeter seal. See

FIGURE 3.5a

d. Seal horizontal pressure plates against the vertical face covers. Tool sealant into the joint.

See

FIGURE 3.5b.

e. Install horizontal face covers, leaving an equal gap at each end. Make sure that the weep hole in the

face cover is on the top.

Backer rod & sealant in cavity

Perimeter seal

Mullion end cap

FIGURE 3.5a

Sealing Top of Captured Verticals

Weep Hole

GLAZING INSTRUCTIONS