Lesson two - processing baselines, continued – Leica Geosystems SKI-Pro User Manual

Page 47

Advertising
background image

Quick Tour II - Post-Processing

47

Getting Started with SKI-Pro-2.5en

In our case the Ambiguity Status is Yes for all points
(baselines) and we can store the coordinates to the
database.

Right-click on the selected points and select Store or

use the toolbar

.

The results of the four baselines are now stored in the
database.

To verify that the baselines have been stored, click the

View/Edit tab at the bottom of the window.

Right-click in the background and select Graphical

Settings... Make sure

GPS is checked.

The following view is displayed:

To complete the network we have to process the remain-
ing two processing runs.

To return to the GPS-Processing View click the

GPS-proc tab.

Right-click on the background and click on Deselect All.

Select the second instant of the points TP214, B215,

B313 as Rover and the point B218 as Reference.

Process and Store the second run.

Finally, Select, Process and Store the remaining

baseline between B313 and TP306.

The following view is displayed:

Lesson Two - Processing Baselines, continued