2: Prepare for Installation

2-1

Chapter 2: Pr epare Bolt-On W eight
Measur ement Sensors
for Installation

This chapter will describe the pre-installation procedures for
L-Cells and Microcells. By verifying the application and
checking the cells before installation, it will ensure proper
installation of working cells that will provide accurate
monitoring of the vessel contents.

Application V erification

Prior to ordering the Bolt-On Sensors, you should have completed the
Application Data Form #97-5092. A copy of the completed
Application Data Form was returned to you with both the order
acknowledgment and equipment shipment. If you cannot locate the
form, contact KM to obtain another copy before you proceed. Review
the information on the form to verify the application details.

Note

If the calculated stress is outside the following ranges, it is
considered a non-standard application. Consult KM before
proceeding.

• L-Cell: Carbon steel vessel — 1,500 psi to 8,500 psi
(1.0 kg/mm

2

- 6.0 kg/mm

2

)

• L-Cell: Aluminum vessel — 1,500 psi to 4,500 psi
(

1.0 kg/mm

2

to 3.2 kg/mm

2

)

• 3-inch Microcell — 2,500 psi to 7,500 psi
(1.8 kg/mm

2

to 5.3 kg/mm

2

)

• 2-inch Microcell — 3,750 psi to 11,250 psi
(2.6 kg/mm

2

to 7.9 kg/mm

2

)

Order V erification

Prior to beginning installation, verify that your order is complete and
assemble additional equipment needed for the installation. If any items
are missing from the order, contact KM before proceeding. Substituting
parts without KM aproval may cause system problems and will void the
warranty.

L-Cell Order

The following items are included with your order for each vessel
(quantities are dependent on vessel data or application):