Chapter 3. L-Cell Installation on Vertical Legs

3-11

Figure 3-20. Wiring Junction Boxes Together — Non-Conduited Installation

Connect 3-Conductor
Cable to TB2

Connect 3-Conductor

Cable from First

Junction Box to TB1

Connect another
3-Conductor
Cable to TB2

Connect Shield Wire

from Both Cables to

Shield Terminal

Connect Shield

Wire (typical)

To L-Cells
(typical)

First
Junction Box

To Next Junction
Box or Signal
Processor

Cable Tray

Figure 3-19. Wiring Junction Boxes Together — Conduited Installation

Connect 3-Conductor
Cable to TB2

Connect another
3-Conductor
Cable to TB2

To Next Junction
Box or Signal
Processor

Connect Shield Wire

from Both Cables to

Shield Terminal

Connect Shield Wire

to Shield Terminal

To L-Cells (typical)

First
Junction Box

Connect 3-Conductor

Cable from First

Junction Box to TB1