9.)

Raise the lift up – keep a close eye as the lower frame enters the enclosure/hole.
Center the closure panel left-to-right and front-to-rear. Tighten the CTB Bracket

and Slider hardware when completed.

NOTE:

• Prepare the ceiling closure panel by painting it to match the existing ceiling.

• Carefully raise the lift using the remote control.

• Finally, adjust the rods so that the ceiling closure panel fits flush with the ceiling.

• When adjusting the Closure Panel, the springs should compress about 1/8” to

1/4”.

¼-20 Rod Nut

Plastic Sleeve

Spring

Flat Washer

¼-20 Nylock Nut

Closure Frame Rod
upper detail

(1522 model)

Closure Frame Rod

lower detail

No longer than 2”

above lift frame

Cut rods to length

for projector