9 Telescopic Flue - Length, Preparation and Installation

9.5 Flue Fitting

With the air duct seams aligned and the flue set to the

required length ‘Y’, mark the securing hole position in the air

duct. Drill a 3mm diameter hole at this position, take care not

to pierce the inner flue duct. Secure with screw provided and

tape the joint, see diagram 9.7.

Fit the sealing collar onto the locating ring on the flue terminal,

see diagram 9.8.

With the flue elbow removed, push the flue assembly into

the wall, externally or internally, until the end of the assembly

protrudes a short way from the inside face of the wall. This

will enable the internal trim ring (if required) to be positioned

and allow the flue assembly to be drawn back up to the flue

elbow.

Secure the flue elbow in position on top of the boiler with the

four screws supplied.

Draw the flue assembly from wall and engage the flue duct

into the elbow and butt fit between the air duct and flue elbow.

Check the correct alignment of the flue.

Fit the securing collar in position, mark through two of the pre

drilled holes in the securing collar. Remove securing collar

and drill two 3mm diameter holes one in the elbow and one in

the air duct, take care not to pierce the inner flue duct. Fit the

securing collar and secure with screws provided, see diagram

9.9.

Slide the internal trim ring back against the wall, securing in

place with a small amount of sealant if required.

The cut ducts must be de-burred and all filings and debris

removed.

Insert the flue duct into the air duct terminal assembly,

remembering to engage the catch within the terminal.

NOTE: If the seals require lubricant to ease installation, do not

use mineral oils or grease, water is recommended.