15 completion of installation – Glow-worm Betacom C User Manual

Page 31

Advertising
background image

31

9 Vertical Flue - Length, Preparation and Installation

Diagram 9.20

14529

Diagram 9.21

14528

Diagram 9.22

12982

9.15 Completion of Installation

With the flue terminal positioned in the roof the length of the

final pipe can be determined. If a telescopic length cannot

be used, then a standard flue length can be cut to make the

correct length. Cut the flue to the desired length measuring

from the ‘O’ ring end and discard the plain end of the tube.

The cuts must be square and made free of burrs to allow

correct assembly.

NOTE: The flue pipe is 10mm longer than the air pipe, see

diagram 9.23.

Carefully push the terminal assembly upwards to allow room

for fitting the final flue piece. Fit a fixing bracket to the terminal

assembly. Pull the terminal assembly down and join to the flue

system. Ensure that the terminal is making a weather tight

seal on the weather collar. Secure the fixing bracket fitted to

the terminal to the roofing struts or a purpose made batton.

Diagram 9.23

12983

Advertising