9

9.17.045

Digital RS232 operation

Digital operation over RS232 can be established

when using the following setup. Using a RS232

cable or a USB-RS232 converter with a PC will

allow you to use (free) Bronkhorst® software for

Windows, such as FlowDDE and FlowPlot. See

also section 3.4.

Digital RS485 operation

With digital operation over RS485 a bus-system with multiple instruments can be set up. See section 3.5 for possible

systems.

2.8

Multi-functional switch operation

Micro-switch operation (single channel versions only)

Using the micro-switch on the instruments, several actions can be monitored and

started. The green LED is used for status indication. The red LED is used for

errors/warnings/messages. The micro-switch can be used to start several

actions, such as auto-zero, restore factory settings and bus-initialisation actions,

if applicable. See specific zero-procedure below and section 3.3 for more details.

Multi-functional switch

Status LED

Error/Warning LED

Rotary switch operation (multi-channel versions only)

Select the communication type and Baud rate with the “COMM. TYPE” switch.

Select the node address with the “MSD” and “LSD” switch (e.g. MSD = 1 and LSD

= 9 selects node 19 for channel 1, but also node 20 and 21 for channels 2 and 3).

See section 3.3 for more details.

2.9

Purging

Do not apply pressure until electrical connections are made. When applying pressure to the system, avoid pressure

shocks in the system and increase pressure gradually. Also decrease pressure gradually when required.

In systems for use with toxic or other dangerous fluids, purging for at least 30 minutes with a dry, inert gas (like

Nitrogen or Argon) is absolutely necessary before use. After use with toxic or other dangerous fluids, complete

purging is also required before exposing the system to air.

Warm-up time

Let the IQ

+

FLOW® warm-up for at least 30 minutes for best accuracy.