Procedure for insulation resistance measurement referring to the previous picture:

Switch situation

Point under test

Measurement result

Judgement of an
installation

Se R

≥ R

LIMITE

OK (end of the test)

1

Turn the switch A,

l D and E off

Take the measurement
on switch A

Se R

< R

LIMITE

Proceed 2

Se R

≥ R

LIMITE

Proceed 3

2

Turn the switch B

off

Take the measurement

on switch A

Se R

< R

LIMITE

INSTALLATION

NOT COMPLYING
WITH STANDARDS

Se R

≥ R

LIMITE

OK (end of the test)

3

Take the measurement

on switch B

Se R

< R

LIMITE

Proceed 4

Se R

≥ R

LIMITE

Proceed 5

4

Turn the switch C

off

Take the measurement

on switch B

Se R

< R

LIMITE

INSTALLATION

NOT COMPLYING
WITH STANDARDS

Se R

≥ R

LIMITE

OK (end of the test)

5

Take the measurement

on switch C

Se R

< R

LIMITE

INSTALLATION

NOT COMPLYING
WITH STANDARDS

Table1:

Table with procedure steps for insulation measurement referred to the

installation reported in Errore. L'origine riferimento non è stata trovata.

Note The switches D and E are those installed near the load having the purpose of
separating it from the installation. In case the above said RCDs do not exist it is
necessary to disconnect the users from the before making the insulation resistance
test.

ATTENTION:
If the installation includes electronic devices, disconnect them from the installation and
in case this is impossible only the test "a" is to be effected, that is to say between
active conductors (which in this case SHALL be connected together) and the earth.