Hea ter inspection and maintenance schedule, Continued) – Munchkin Gas-Fired Hot Water Circulating Heater User Manual

Page 69

Advertising
background image

68

GAS-FIRED HEATER

Installation Manual

Condensate

1st Year

2 Year

3 Year

4 Year*

Condensate Neutralizer

Check condensate neutralizer, replace if necessary

Condensate Cup

Disconnect condensate cup, clean out dirt, fill with water to level of outlet and re-install ( Note: you

must verify the flow of condensate, making sure that the cup is connected properly during final

inspection.)

Gas

Pressure

Measure incoming gas pressure (from 3.5" to 14" W.C.)

Pressure Drop

Measure drop in pressure on light off (no more than 1" W.C.)

Check gas pipe for leaks

Check piping for leaks, and verify they are all properly supported

Combustion

Check CO/CO2 Levels

Check levels of CO and CO2 in Exhaust (See start up section 12 fig 12-1 for ranges) record at high

and low fire

Safeties

ECO (Energy Cut Out)

Check continuity on Flue and Water ECO, replace if corroded

Water Pressure Switch

Check operation , check for signs of leakage, replace if corroded

Thermistors

Check wiring, verify through ohms reading (see chart part 14 Fig. 14-3)

Final Inspection

Check List

Verify that you have completed the entire check list WARNING: FAILURE TO DO SO COULD

RESULT IN DEATH OR SERIOUS INJURY.

Homeowner

Review, with the homeowner what you have done

*

NOTE

:

CONTINUE

MAINTENANCE

BEYOND

THE

4TH

YEAR

IS

REQUIRED

ON

A

Y

EARLY

BASIS.

Date last completed

Inspection Activities

HEA

TER INSPECTION AND MAINTENANCE SCHEDULE

(CONTINUED)

Advertising