Installation Guide TLE Series 225 - 500 UL S1

TLE Series 400 & 500 Access to the bus bars for the cable connections

Fig. 4.8-2 TLE Series 400 & 500 - Access to connection bus bars


To access Input, Output and Battery connections
proceed as follows:

Remove the front protection panel A.

Bottom entry cables: remove the plate B.

Top entry cables: remove the plate C.

NOTE !

For

UPS

correct

operation, the input
utility phase rotation
must be clock-wise.



CAUTION !

Panel “A, B and C” should never be removed or replaced with power applied to the
UPS.
These panels are in close proximity to 480V live buss bars.
Always disconnect the rectifier, bypass, load and battery sources from the UPS
before removing or replacing these panels.
If not serious injury or death could occur!

Q1

I ON

0

O

FF

A

B

C

Utility mains / Battery / Output load

Bottom entry cables

TLES_UL_400-

500_S1_U

PS connec

tion_01US

1

2

Q2

I ON

0

O

FF

E

PO

E

PO

- +

Utility mains / Battery / Output load

Top entry cables

!

Please remove

the plate (B) before
drilling any wholes

!

It's MANDATORY REMOVE

the base reinforcement (C)
See Chapter 4.4.1

D