9 rpa parallel system connection, 1 power wiring of parallel units, Rpa parallel system connection – GE Industrial Solutions TLE Series 225-500 Installation Guide User Manual

Page 42: Power wiring of parallel units

Advertising
background image

Critical Power

Modifications reserved

Page 42/54

GE_UPS_ISG_TLE_SUL_M22_M50_1US_V010.docx

Installation Guide TLE Series 225 - 500 UL S1

4.9 RPA PARALLEL SYSTEM CONNECTION

WARNING !

This operation must be performed by trained personnel before the initial start-up
(ensure that the UPS installation is completely powered down).



4.9.1 Power wiring of parallel units

To guarantee good Load sharing between the units of a Parallel System, we recommend that the cable
length from the input distribution board (5) to the output distribution board (9) is equal for each unit (a+b
= c+d = e+f = g+h = i+l = m+n = o+p = q+r).

Tolerance: +/-10%.

The AC input power of the Bypass must be the same for all units of the Parallel System - no phase shift
allowed between units.

NOTE !

It is strongly recommended that no transformers, automatic circuit breakers or
fuses should be inserted between the unit’s output and the Load
common bus bars.
However, it is recommended that a disconnection or isolation switch is installed in
order to totally isolate a unit if needed.


Verify that power wiring and control wiring run in separate conduits or cable trays.
The power wiring requires two separate conduits: one for input and one for output cables.

Fig. 4.9.1-1 Power wiring of RPA Parallel System

1 = Rectifier
2 = Inverter
3 = Automatic Bypass
4 = Manual Bypass
5 = Input Utility Distribution
6 = Unit Output Load
7 = External Battery MCB
8 = External Battery

9 =

Common bus bar and
Output Load Distribution

= UPS number 1

= UPS number 2

= UPS number 3

= UPS number 4

= UPS number 5

= UPS number 6

Advertising