Appendix – HT instruments SIRIUS87 User Manual

Page 73

Advertising
background image

SIRIUS

87

EN - 71

11. APPENDIX

11.1. LOW

: CONTINUITY MEASUREMENT ON PROTECTIVE CONDUCTORS

Purpose of the test is to check the continuity of:
a) protective conductors (PE), main equalizing potential conductors (EQP), secondary

equalizing potential conductors (EQS) in TT and TN-S systems.

b) neutral conductors having functions of protective conductors (PEN) in TN-C system.

NOTE: This test is to be preceded by a visual check verifying the existence of yellow-

green protective and equalizing potential conductors as well as compliance of the
sections used with the standards’ requirements.


INSTALLATION PARTS TO BE CHECKED

Examples for continuity measurement on conductors

Check the continuity among:
a) earth poles of

all the plugs and earth collector or node.

b) earth terminals of class I instruments (Boiler etc.) and earth collector or node.
c) main external masses (water, gas pipes etc.) and earth collector or node.
d) auxiliary

external masses to the earth terminal.

Connect one of the
test lead to the
external mass (in
this case the water
pipe) and the other
to the earth
installation using
for example the
protective
conductor of the
closest FM socket.

Connect one of the
test lead to the
protective
conductor of the
FM socket and the
other to the
equalising potential
node of the earth
installation.