Scale Installation

17

2.9

1 2 V

Load Cell

Homerun

Cable

Reed
Switch

920i Electronics Installation

Figure 2-16. Exterior Electronic Weigh Center Connection

The scale electrical system consists of an electronic weigh center, load cells, reed switch and junction box. The

load cells are connected to the indicator via a summing board located in a junction box. The reed switch is routed

directly to the weigh center and connected to the appropriate wires. The system is powered from a fused 12V

power supply.

2.9.1

Disassembly of Indicator Panel











Figure 2-17. Removal of Indicator

To access the terminal switches for installation of Magnetic Alarm Switch or wiring homerun and power cable:

Note

WARNING

Procedures requiring work inside the indicator must be performed by qualified service personnel only.

Before opening the unit, ensure the power is disconnected.

1. Release latches (2) on each side and raise the cover (3).
2. Remove the screws (4) holding the front panel to the weigh center box (1).
3. Remove the indicator assembly (5) from the weigh center.

Reassemble by reversing the order above.