11.4

Press the check mark () button on the Touch Screen Display. The following screen will be displayed.

After you confirm that the DE is added, the Clamp Bar D button on the Control
Panel is disabled until the SDF process completes.

12. Install IDF Flow-thru bags on the ANKOM

TDF

Dietary Fiber Analyzer.

12.1

Gently pull the black IDF Delivery Nozzle out toward you.

12.2

Place a labeled IDF Flow-Thru bag up underneath the Delivery Nozzle so that the Delivery Nozzle is inside the
top part of the bag. Pull the bag up so that the top of the bag is about 35 mm (1.375 inches) above the top of
Clamp Bar A and return the Delivery Nozzle to its original position. This will hold the back of the bag in place.

12.3

With the bag held by the Delivery Nozzle, center it horizontally between the Centering Lines on the back part of
Clamp Bar A.

For proper mixing during the IDF process the IDF Flow-thru bags must be
horizontally centered over the Heating Paddles and between the Centering Lines on
the back part of Clamp Bar A.

IDF Flow-Thru Bags (and clamp bar B) installed?

AOAC 985.29 TDF

Centering Lines

Heating Paddle