TABLE 3 - CRATED DIMENSIONS

Carrier

Height

Depth

Width

Weight

(in.)

(in.)

(in.)

(lb.)

26H5 Machine Section

43-1/2

23-1/2

28-1/2

307

26H3 Machine Section

43-1/2

23-1/2

28-1/2

236

100 lb. Bln

31-1/2

27

26

95

160 Lb. Bin

39-1/2

26-1/2

25

112

240 Lb. Bin

39-1/2

26-1/2

35

142

500 Lb. Bin

45-1/2

34-7/8

49-1/2

225

Heat Interchange!

22-1/2

17

5

18

4. UNCRATE THE BIN

Uncrate the bin first since it serves as the base

for the unit.

5. INSTALL LEVELING SCREWS

Support the bin with the four leveling screws sup­
plied with the bin. See Fig. 1. The top of the bin
can be used for leveling.

6. UNPACK AND MOUNT THE HEAT

INTERCHANGER

Remove the interchanger and parts from the carton.
Mount the heat interchanger on the back of the bin
with the 6 sheet metal screws in the paper envelope.
The position of the interchanger on the back of the

bin is shown in Fig. 2.

HEAT INTERCHANGER

DRAIN

HEAT INTERCHANGER
CLEAN

t

FIG. 1 - LEVELING SCREWS INSTALLED

FIG. 2 - POSITION OF HEAT INTERCHANGER

ON THE BIN