The time required to generate the vacuum is

dependent on the final pressure pipe volume of the

indoor units and the length of the refrigerant piping.

This always takes at least 60 minutes. Once any

foreign gases and humidity have been completely

extracted from the system, the valves on the pres-

sure gauge station are closed and the valves on

the outdoor unit are opened as described in the

"Commissioning" section.

Commissioning

NOTICE!

Commissioning should only be performed and

documented by specially trained personnel.

Observe the operating manual for the indoor

units and outdoor components when commis-

sioning the entire system.

Once all the components have been connected

and tested, the system can be put into operation. A

functional check should be performed to verify its

correct function and identify any unusual operating

behaviour prior to handing it over to the operator.

This check is dependent on the installed indoor

unit. The processes are specified in the operating

manual for the indoor units being commissioned.

Functional checks and test run

Check the following points:

n

Leak-tightness of the refrigerant piping.

n

Compressor and fan running smoothly.

n

In heating mode, the indoor unit outputs

warmer water and the outdoor unit outputs cold

air.

n

Function test of the indoor unit and all program

sequences.

n

Check of the surface temperature of the suc-

tion pipe and that the vaporiser is not over-

heating. To measure the temperature, hold the

thermometer to the suction pipe and subtract

the boiling point temperature reading on the

pressure gauge from the measured tempera-

ture.

n

Record the measured temperatures in the

commissioning report.

Function test of heating operating mode

1.

Remove the protective caps from the valves.

2.

Start the commissioning procedure by briefly

opening the shut-off valves on the outdoor

unit until the pressure gauge indicates a

pressure of approx. 2 bar.

3.

Check all connections for leaks with leak

detection spray and suitable leak detectors. If

no leaks are found, fully open the shut-off

valves by turning them anti-clockwise using a

spanner. If leaks are found, draw off the

refrigerant and rework the defective connec-

tion. It is imperative that the vacuum creation

and drying steps are repeated!

4.

Activate the main circuit breaker or fuse (to

be provided by the customer).

5.

Program the Smart Control.

6.

Switch on heating mode

Due to the turn on delay, the compressor

will start up a few minutes later.

7.

Check all regulating, control and safety

devices for function and correct adjustment

during the test run.

8.

Measure all cooling data and record the

measured values in the commissioning

report.

9.

Remove the pressure gauge.

Final tasks

n

Use the Smart Control to set the target temper-

ature to the required value.

n

Re-install all disassembled parts.

n

Familiarise the operator with the system.

NOTICE!

Check that the shut-off valves and valve caps

are tight after carrying out any work on the

cooling cycle. Use appropriate sealant prod-

ucts as necessary.