Install the drain line, Verify coil hand designation, Check the coil for leaks – Greenheck Fan Make-Up Air Unit 470658 MSX User Manual

Page 14: Connect the supply and return lines

Advertising
background image

14

®

Model MSX Make-Up Air

for one minute, the system is ready to be charged or
refrigerant in another portion of the system can be
opened to the coil. A steady rise in microns would
indicate that moisture is still present and that the coil
should be further vacuumed until the moisture has
been removed.

8. Install the Drain Line

Connect an
unobstructed drain
line to the drain
pan. A trap should
be used to prevent
sewer gas from being
drawn into the unit.

NOTE

Failure to obtain a high vacuum indicates a great

deal of moisture or a small leak. Break the vacuum

with a charge of dry nitrogen or other suitable

gas and recheck for leaks. If no leaks are found,

continue vacuuming the coil until the desired

vacuum is reached.

IMPORTANT

All traps must be installed below the roof line or be
otherwise protected from freezing.

6 in. min.

6 in. min.

Drain Trap

6 in. min.

6 in. min.

Drain

Trap

Installation of Chilled Water Coil

Piping (optional)

1. Verify Coil Hand Designation

Check the coil hand
designation to ensure that
it matches the system.
Coils are generally
plumbed with the supply
connection located on
the bottom of the leaving
air-side of the coil and the
return connection at the top of the entering air-side
of the coil. This arrangement provides a counter flow
heat exchanger and positive coil drainage.

2. Check the Coil for Leaks

Pressurize the coil to 100 psig with dry nitrogen or
other suitable gas. The coil should be left pressurized
for a minimum of 10 minutes. If the coil holds the
pressure, the hook-up can be considered leak free.
If the pressure drops by 5 psig or less, re-pressurize
the coil and wait another 10 minutes. If the pressure
drops again there is likely one or more small leaks
which should be located and repaired. Pressure losses
greater than 5 psig indicate a large leak that should be
isolated and repaired.

3. Connect the Supply and Return Lines

Connect the supply and return lines as shown above.

4. Install the Drain Line

Connect an unobstructed
drain line to the drain pan.
A trap should be installed
to prevent sewer gas from
being drawn into the unit.

Hot Return
Connection

Cold Supply
Connection

Entering Air

Leaving Air

IMPORTANT

Guidelines for the installation of the cooling coil
have been provided to insure proper performance
of the coils and their longevity. These are general
guidelines that may have to be tailored to meet the
specific requirements of any one job. As always,
a qualified party or individual should perform the
installation and maintenance of the coil. Protective
equipment such as safety glasses, steel toe boots
and gloves are recommended during the installation
and maintenance of the coil.
When installing couplings, do not apply undue
stress to the connection. Use a backup pipe
wrench to avoid breaking the weld between the coil
connection and the header.
All field piping must be self-supporting. System
piping should be flexible enough to allow for the
thermal expansion and contraction of the coil.

IMPORTANT

All traps must be installed below the roof line or be
otherwise protected from freezing.

Advertising